SOLUTION: Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Algebra.Com
Question 1027713: Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Found 2 solutions by macston, Edwin McCravy:
Answer by macston(5194)   (Show Source): You can put this solution on YOUR website!
.
x=number of workers for 12 hours
.
. Cross multiply.
.
. Divide each side by 28.
.
=1.29 workers
.

Answer by Edwin McCravy(20081)   (Show Source): You can put this solution on YOUR website!
The other tutor's answer is very wrong.

Three workers can do a job in 28 hours. How many more workers
are needed to do this job in 12 hours?
The fewer workers there are the more the hours that are required, 
and the more workers there are, the fewer hours that are required.

Therefore workers and hours are inversely proportional.

The word "inversely" is a form of the word "invert".
So we invert one of the fractions in the proportion. It doesn't
matter which one we invert.









7 workers are required, so we need 7-3 or 4 more workers.  

Edwin

RELATED QUESTIONS

Three workers are named X ,Y,and Z. Suppose that together X and Y and can do a job in 4... (answered by Earlsdon)
If a certain job can be finished by 18 workers in 26 days. How many workers are needed to (answered by robertb)
Three workers have to do a certain job. The first worker can finish the job in 8 hours.... (answered by ikleyn,greenestamps)
Three workers are named x, y and z . suppose that together x and y can do a job in 4... (answered by richwmiller)
Three workers can do a job in 12 days. Two of the workers work twice as fast as the... (answered by josgarithmetic)
8 person work crew completes a job in 18 hours. What is the fewest number of workers... (answered by ankor@dixie-net.com)
PLS help me on this word problem.. 18 workers can finish a job in 5 days.how many workers (answered by nerdybill)
Three workers set out to plaster a ceiling. One can do the job alone in 2 hours, one in... (answered by edjones)
Three workers can build 8 chairs in 4 hours. How many workers are needed to build 16... (answered by Boreal)