Question 1025640: please if it takes 2 works 2 weeks to complete a task, how many days will it take 5 works to complete same task
Answer by Fombitz(32388)   (Show Source): You can put this solution on YOUR website!
The whole job needs 4 worker-weeks to complete.
If you have 5 workers then,


It only take week to complete.

RELATED QUESTIONS

By working 8 hours per day, Marley's team can complete a task in 15 1/2 days. Bill's... (answered by Boreal,greenestamps)
How long will it take 20 machines to complete a task, given that it takes 12 days for 5... (answered by rfer)
If it takes 20 people to complete as task in 12 days. How many people will it take to... (answered by Edwin McCravy)
How long will it take 4 workers to complete a task, given that it takes 6 days for 6... (answered by Simnepi)
How long will it take workers to complete a task, given that workers can complete the... (answered by JulietG)
How many workers will be needed to complete a task in 3 days, given that it takes 10 days (answered by edjones)
how many machines will it take to complete a task in 3 days, considering it takes 10 days (answered by stanbon)
Mary takes 3 hours to complete a task. Mary and Jim together take 2 hours to complete the (answered by checkley71)
Hi I really need help with these questions please. Could someone show their solution too... (answered by richwmiller)