SOLUTION: 55 men can finish a piece of work in 42 days. How many additional men must be added to complete the work 9 days earlier..?

Algebra.Com
Question 1024283: 55 men can finish a piece of work in 42 days. How many additional men must be added to complete the work 9 days earlier..?
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
1 man can finish the job in times that time
or: days
This is: [ 1 job done ] / [ 2310 days ]
------------------------------
Let = additional men to be added
1 man can do this job in times
the time it takes men
rate for 1 man =
----------------------
These rates for 1 man are the same, so:





An additional 15 men are needed to
finish the job 9 days earlier
-------------
check:
rate for 1 man is:



OK

RELATED QUESTIONS

28 men can complete a piece of work in 21 days. How many more men must be hired to... (answered by josgarithmetic)
20 men can do a piece of work in 24 days. After working for 6 days, additional number of... (answered by richwmiller)
a piece of work can be done by 40 men in 48 days. after 15 days, 18 men were transferred... (answered by stanbon)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)
A certain number of men can finish a piece of work in 10 days. If however there were 10... (answered by ankor@dixie-net.com)
If 20 men complete one third of a piece of work in 20 days, how many more men should be... (answered by jorel1380)
A piece of work can be done in 48 days by 40 men. After 15 days, 16 men were transferred. (answered by stanbon,jrfrunner)
A piece of work can be done by 40 days by 25 men. After 16 days, 13 men are transferred.... (answered by Finavon)
if 20 men can do a piece of work in 8 days, then how many men can finish the same work in (answered by ankor@dixie-net.com)