SOLUTION: 10 workers can do work in 20 days , when they start the work , after how many days should 5 workers leave the work so that the work would be finished in 35 days ?

Algebra.Com
Question 1024218: 10 workers can do work in 20 days , when they start the work , after how many days should 5 workers leave the work so that the work would be finished in 35 days ?
Found 2 solutions by josgarithmetic, MathTherapy:
Answer by josgarithmetic(39623)   (Show Source): You can put this solution on YOUR website!
This is ambiguous. I will take as t days with 10 workers, and 35-t days with the remaining 5 workers. This makes for a total job time of 35 days from start to finish.

, accounts for "one whole work".

Look at first sentence.
Let r be rate for one worker, jobs per days.

.


Use the needed data in the work-rates rule.

If this makes sense, and especially if you can formulate the equation on your own, then enough help done; just solve for t.

Answer by MathTherapy(10555)   (Show Source): You can put this solution on YOUR website!

10 workers can do work in 20 days , when they start the work , after how many days should 5 workers leave the work so that the work would be finished in 35 days ?
After  on the job, 5 workers can leave, and the remaining 5 workers will take 35 days to complete the  remaining work. 

RELATED QUESTIONS

12 workers can do a piece of work in 16 days if 12 more workers are added in how many... (answered by Cromlix)
12 workers can do a piece of work in 20 days.How many workers should be added to complete (answered by richwmiller)
If 9 workers complete the work in 10 days how many workers will complete the same work in (answered by josgarithmetic,josmiceli)
If 10 workers do a certain work in 16 days, than in how many days the same work will be... (answered by josgarithmetic)
16 workers can complete a piece of work in 30 days.After working for 10 days, 4 more... (answered by richwmiller,ikleyn)
In Ngomongo village a piece of work can be completed by 45 workers in 10 days .They work... (answered by srinivas.g,macston,josmiceli,MathTherapy)
28 workers can finish a piece of work in 45 days. a)How many workers are needed if the... (answered by richwmiller,rothauserc)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days. They work... (answered by richwmiller)
1. 20 men can do a piece of work in 30 days.After working for how many days should 5 men... (answered by josgarithmetic)