SOLUTION: A does 7/10 of a piece of work in 14 days. He then calls B, and they finish the work in 2 days. How long would B take to do the work by himself?
Algebra.Com
Question 1022954: A does 7/10 of a piece of work in 14 days. He then calls B, and they finish the work in 2 days. How long would B take to do the work by himself?
Answer by fractalier(6550) (Show Source): You can put this solution on YOUR website!
The normal set up for work problems is
In our problem, A completes 7/10 of the job in 14 days. That means he could do it all in 20 days.
Our t in the set up is 2 days, and the 1 job in the set up is only 3/10 job here.
So our equation looks like this
and when you work that out you find
B = 10 days
RELATED QUESTIONS
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
A does 80% of a work in 20 days. He then calls in B and together they finish the... (answered by dkppathak)
A does 4/5 of a work in 20 days.He then calls in B and together finish the remaining work (answered by ewatrrr)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work... (answered by richwmiller)
A,B,C can finish a piece of work in 60 days. They work together for 10 days after which A (answered by htmentor)
A & B together can paint a room in 18 days . they work together for 8 days and then b... (answered by richwmiller,josmiceli)
A can do a piece of work in 4 1/2 days. After he has worked three days, B joined him and... (answered by richwmiller)
Person A can do a piece of work in 10 days. After he has worked for 2 days, B comes and... (answered by scott8148)
Bigyan can do of a work in 9 days. He calls Amar to finish the remaining work. They work (answered by Collinwilfixyouuprealnice)