SOLUTION: if it took 8 builders 25 days to build a house how long would it take 10 builders to do the same job.

Algebra.Com
Question 1021596: if it took 8 builders 25 days to build a house how long would it take 10 builders to do the same job.
Answer by robertb(5830)   (Show Source): You can put this solution on YOUR website!
It would require 8*25 = 200 man-days to build the house.
==>
<==>
==> x = 20 days.

RELATED QUESTIONS

If 13 builders took 6 months to build a house how long will 10 builders take to build the (answered by Boreal,addingup)
It takes 5 builders 48 days to build a house. How long would it take to build if there... (answered by Edwin McCravy)
8 builders can build a house in 40 days, how long will it take for 2 builders to build a... (answered by Theo,josgarithmetic,greenestamps,ikleyn)
Hi-Please help me with the following It takes a team of 13 builders 6 months to build a (answered by rothauserc)
4 builders take 10 days to build a certain wall. How long will it take for 5 builders to... (answered by richwmiller)
Six builders take 1 hour to build the same wall. How long would it take for 2 builders... (answered by ikleyn)
Six builders worked 8 hours a day for 10 days to complete a job. If eight builders worked (answered by ankor@dixie-net.com)
A building supervisor measured the time it took in days for two builders to build the... (answered by vleith)
What is the proportion of the 6 builders to build a wall in 15 day and 10 builders to... (answered by ikleyn)