SOLUTION: Carpenter A can build a chair in 6 hours while carpenter B can build the same chair in 9 hours. If Carpenter A starts working on a chair for two hours and then carpenter B joins hi
Algebra.Com
Question 1020353: Carpenter A can build a chair in 6 hours while carpenter B can build the same chair in 9 hours. If Carpenter A starts working on a chair for two hours and then carpenter B joins him, how long will take for the two of them to finish the rest of the job? And. 12/5 hours.
Found 2 solutions by josgarithmetic, josmiceli:
Answer by josgarithmetic(39620) (Show Source): You can put this solution on YOUR website!
RT=J relates work rate, time, amount of job or work. Your example uses 1 for the amount of work of making ONE chair.
The rate for more than one identical working agents acting simultaneously on the same task is the sum of their rates.
Carpenter Rates
A
B
How long t, for the two of them to finish AFTER carpenter B joins?
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
What fraction of the job does A
get done in 2 hrs?
-----------------
A's rate of working:
[ 1 chair ] / [ 6 hrs ]
That means 2/3 of the chair remains
to be built
-----------------
B's rate of working:
[ 1 chair ] / [ 9 hrs ]
Let = time in hrs for them to
finish the chair working together
-----------------------------
Add their rates of working to get
rate working together
Multiply both sides by
hrs
------------------
check answer:
OK
RELATED QUESTIONS
a carpenter can build a desk in 32 hours. After 8 hour he is joined by a second carpenter (answered by macston,josgarithmetic)
A carpenter can build a tool shed three times as fast as his apprentice. Working... (answered by richwmiller)
By checking work records, a carpenter finds that Jane can build a small shed in 12 hours. (answered by stanbon)
A carpenter can build 15 toolsheds three times as fast as his apprentice. Working... (answered by TimothyLamb,josgarithmetic)
"A carpenter can build a certain type of patio to cover in 6 hours. his partner takes 8... (answered by rothauserc)
Hello, I am having trouble understanding and solving this problem:
A furniture company (answered by solver91311)
Hello, I am having trouble understanding and solving this problem:
A furniture company (answered by KMST)
A carpenter and his partner can put up a patio cover in 3 3/7 hours. If the partner needs (answered by ankor@dixie-net.com)
A carpenter had two apprentices for a job. The carpenter worked 6 hours longer than the... (answered by josgarithmetic)