SOLUTION: A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if

Algebra.Com
Question 1018635: A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?
(A) 5 days (B) 2 days
(C) 3 days (D) 1 day

Answer by josgarithmetic(39623)   (Show Source): You can put this solution on YOUR website!
Question 1018635

RT=J relates work rate for specific number of agents doing work. For 1 job being the focus, J=1.
If r is the rate of work for 1 man, then rate must be multiplied by the number of men doing
work together.

;
The situation done is the splitting of the job into two parts. That is the five 30 men for only
25 days, and then the increased number of men for for 12 days, to finish the one job.
Note that "one day earlier", would be 37 days total work time.

.
Either equation will allow finding the one-man rate, r, and this MUST be found to be the same
value for both equations. That should be the first goal in solving the problem.

RELATED QUESTIONS

30 men can do a work in 36 days. After 30 days more men are employed and work is done 2... (answered by josmiceli)
An MNC company hired 25 men to do a work in 32 days.After 16 days it employed 5 more men... (answered by richwmiller)
20 men can do a piece of work in 24 days. After working for few days,4 men are added and... (answered by fractalier)
After a certain number of men had been employed on a job for 24 days and had finished... (answered by ewatrrr,josmiceli)
A contractor undertook a certain work to be done in 80 days and employed 72 men to do it. (answered by ankor@dixie-net.com)
A contract is to be completed in 56 days and 104 men were set to work, each working 8... (answered by josgarithmetic)
1. 20 men can do a piece of work in 30 days.After working for how many days should 5 men... (answered by josgarithmetic)
A contractor undertook to build a building in 52 days and employed 24 men to work. Only... (answered by ankor@dixie-net.com,josgarithmetic)
a contractor got a contract to build a building in 30 days and employed 20 men to do the... (answered by ankor@dixie-net.com)