Question 1014912: Gary hired 10 workers to finish the repairs of his house in 24 days. How many workers should be hired if he wants to finish the repair in 48 days? Please answer it. Thank You. God Bless
Answer by josgarithmetic(39618) (Show Source): You can put this solution on YOUR website!
Twice the number of days, HALF the number of workers, so 5 workers. Did you need to use algebra?
RELATED QUESTIONS
Five workers have been hired to complete a job. If one additional worker is hired, they... (answered by Edwin McCravy,math_tutor2020,josgarithmetic,ikleyn)
three workers can paint a house in 14 days. assuming that the workers work at the same... (answered by josmiceli)
Five workers have been hired to complete a job. If one additional worker is hired, they... (answered by ikleyn,math_tutor2020)
A crew of ten workers was hired to complete a job in 8 days. After working for two days,... (answered by josmiceli,MathTherapy)
a king hires a crew of 30 workers, who can build a castle wall in 60 days. However, 10... (answered by lwsshak3,josmiceli)
If it takes 3 days for 10 workers to finish building one house, how many days will it... (answered by scott8148,Edwin McCravy)
If it takes 3 days for 10 workers to finish a house, how many days will it take 15... (answered by ankor@dixie-net.com)
36 people can construct a house in 15 days but the owner would like to finish the work in (answered by Glaviolette,ikleyn,htmentor)
if 3 workers can finish painting a house in 2 days, how many days will it take 6 workers (answered by josgarithmetic,josmiceli,ikleyn)