SOLUTION: Mower A can mow the village park in 3 hours and Mower B can mow the park in 2 hours. At 7 am Mower A began to mow the park and was joined by Mower B at 7:30 am. At what time was th
Algebra.Com
Question 1011170: Mower A can mow the village park in 3 hours and Mower B can mow the park in 2 hours. At 7 am Mower A began to mow the park and was joined by Mower B at 7:30 am. At what time was the job completed?
Answer by Boreal(15235) (Show Source): You can put this solution on YOUR website!
mower A does 1/3 of the village park every hour.
mower B does 1/2
x=number of hours for mower a
x/3 + (x-0.5/2=1, where 1 is the whole park
2x+3x-1.5=6
5x=7.5
x=1.5 hours
done at 8:30 am
1.5/3 for mower a (50%)
1/2 for mower B is (50%)
RELATED QUESTIONS
Lynn can mow the lawn in 3 hours using a riding lawn mower. Her brother can mow the... (answered by venugopalramana)
lynn can mow the lawn in 3 hours using a riding lawn mower. Her brother can mow the same (answered by checkley71)
Katrina can mow the lawn in 2 hours. It takes her brother 3 hours to mow the lawn. When... (answered by stanbon)
Sidney can mow the law in 4 hours using her riding mower. Her son can mow the same lawn... (answered by richwmiller)
a push mower can mow a large area for 6 hours where as a mower with a riding mower van... (answered by josmiceli)
When Mike uses a riding mower, it takes him 3 hours to mow his lawn. When he uses a push (answered by ewatrrr)
Moe can mow a field with his mower in 3 hours by himself. Curly can mow the same field... (answered by Fombitz)
I want to mow my lawn this summer but I need a new lawn mower. I can choose a riding... (answered by stanbon)
I want to mow my lawn this summer but I need a new lawn mower. I can choose a riding... (answered by stanbon)