SOLUTION: Tom takes 3 days to do a piece of work while jerry takes only one day for the same. Together, they both can finish the job in 15 days. In how many days tom will finish the work?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: Tom takes 3 days to do a piece of work while jerry takes only one day for the same. Together, they both can finish the job in 15 days. In how many days tom will finish the work?      Log On


   



Question 1010621: Tom takes 3 days to do a piece of work while jerry takes only one day for the same. Together, they both
can finish the job in 15 days. In how many days tom will finish the work?

Answer by ikleyn(52792) About Me  (Show Source):
You can put this solution on YOUR website!
.
Tom takes 3 days to do a piece of work while Jerry takes only one day for the same. Together, they both
can finish the job in 15 days. In how many days Tom will finish the work?
---------------------------------------------------------------
The key to the solution of the problem is to recognize (to realize) that there is the "entire job" and "the piece of job". 

Regarding "the piece of work", Tom's rate of work is 1%2F3 of "the piece of work" per day.

Jerry's rate of work is 1%2F1 = 1 of "the piece of work" per day, which means "one piece of work" per day.

Working together, these personages make 1%2F3+%2B+1 = 4%2F3 of "the piece of work" per day.

Hence, they spend 3%2F4 of the day, or 0.75 of the day, to complete this "piece of work", working together.

Since the entire job requires 15 day for Tom and Jerry to complete it working together, it means that the entire job is 
in 15%2F0.75 = 20 times larger (greater) than "the piece of work". Or, in other words, the entire work is equivalent to 20 "pieces of work".

Knowing it, you will easily find the answer to the question in the claim:

Tom will finish the job in 20*3 = 60 days working alone.

highlight%28Send_more_cats%21%29.

I want to say highlight%28Send_more_problems%21%29 :)