SOLUTION: A crew of men takes 1 hour 45min. to complete a job. How many jobs can it complete in 4 1/2days? (assume an 8 hour working day.)

Algebra.Com
Question 1003643: A crew of men takes 1 hour 45min. to complete a job. How many jobs can it complete in 4 1/2days? (assume an 8 hour working day.)
Answer by josgarithmetic(39626)   (Show Source): You can put this solution on YOUR website!
4&1/2 days means hours. This is 36 hours.


A little more than 20.5 jobs.

RELATED QUESTIONS

A 3-men crew can do a certain job in 4 hours, while it takes a 4-men crew to do the same... (answered by ankor@dixie-net.com)
5 men can complete a job in 4 days.In how many days can 10 men working at 1/4 of the... (answered by josmiceli)
5 men can complete a job in 4 days. How many days can 10 men working at 1/4 of the... (answered by josgarithmetic)
A crew of 6 can complete a job in 8 hours. How many hours would it take a group of 4 to... (answered by rfer,vleith)
If it takes 8 men to complete a job in 8 days, how many days would it take 1... (answered by stanbon)
Twenty men did 1/4 of a job in eight days. Then it became necessay to complete the job... (answered by ankor@dixie-net.com)
Twenty men did 1/4 of a job in 8 days. Then, because of an emergency, it became necessary (answered by ankor@dixie-net.com)
14 men took 6 hours 40 min to complete a job a. How long will it take 8 men, working at... (answered by josgarithmetic)
Luke,Eddie, and Ryan can complete a job in 1 hour and 20 minutes if they work together.... (answered by alicealc,richwmiller)