SOLUTION: When workers A and B work together, they can finish the flooring of a house in 6 days.When worker A works alone, he takes 5 days less than worker B to finish the flooring of the ho

Algebra.Com
Question 1002532: When workers A and B work together, they can finish the flooring of a house in 6 days.When worker A works alone, he takes 5 days less than worker B to finish the flooring of the house. How many days does worker A and worker B needs to finish the flooring of the house if they work alone?
Found 2 solutions by josgarithmetic, stanbon:
Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
WORKER        RATE in JOB/DAY
A              1/(x-5)
B              1/x
A&B            1/6

The rate of agents acting together on the same job is the sum of the individual rates.


Find the value or solve for x.

Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
When workers A and B work together, they can finish the flooring of a house in 6 days.When worker A works alone, he takes 5 days less than worker B to finish the flooring of the house. How many days does worker A and worker B needs to finish the flooring of the house if they work alone?
-----
Together rate:: 1/6 job/day
Worker B rate:: 1/x job/day
Worker A rate:: 1/(x-5) job/day
-----
Equation:
rate + rate = together rate
1/x + 1/(x-5) = 1/6
---------
6(x-5) + 6x = x(x-5)
------
12x - 30 = x^2 - 5x
------
x^2 -17x + 30 = 0
------
(x-15)(x-2) = 0
---
Realistic answer:
x = 15
-----
B time = x = 15 days to do the job alone
A time = x-5 = 10 days to do the job alone
----------------------------
Cheers,
Stan H.
------------

RELATED QUESTIONS

A and B, when work together, complete the flooring of a room in 6 days. When A works... (answered by ikleyn)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days. They work... (answered by richwmiller)
When A,B and C work together, they can finish installing the garden in 3 days. The job... (answered by ikleyn)
Workers A and B can complete a particular job if they work together for 12 days. If A... (answered by richwmiller)
Jessie and Mark are planning to paint a house together. Jessie thinks that if he works... (answered by jorel1380,MathTherapy)
Workers A and B can complete a particular job if they work together for 12 days. If A... (answered by stanbon)
When working together worker A and worker B take 8 hours to complete a project.Today they (answered by ankor@dixie-net.com)
when a b and c work together they finish installing a garden in 3 days. The job could be... (answered by ikleyn)
Please solve this question : two persons A and B together can do work in 10 days. the... (answered by richwmiller)