SOLUTION: 1. 20 men can do a piece of work in 30 days.After working for how many days should 5 men leave the work so that the entire work will be completed in 35 days?
2. 20 men can do a pi
Algebra.Com
Question 1001833: 1. 20 men can do a piece of work in 30 days.After working for how many days should 5 men leave the work so that the entire work will be completed in 35 days?
2. 20 men can do a piece of work in 24 days.After working for few days , 4 men are added the work was finished 3 days earlier.After how many days were 4 men added?
Answer by josgarithmetic(39617) (Show Source): You can put this solution on YOUR website!
Helping here for #2, and you should try to work through #1 yourself.
One man rate is r.
The first sentence gives , for the 1 job to be done.
The second sentence uses an unknown amount of time, t, after which men are added (4 of them) to finish the job in 3 days. This work was split into two parts, this way:
.
If all of this is well understood, then you can continue. The question asks for the value of t. The value for rate r will come from the equation from the first sentence.
System of equations if this is more comfortable to see,
RELATED QUESTIONS
20 men can do a piece of work in 24 days. After working for few days,4 men are added and... (answered by fractalier)
20 men can finish 1/6 of a piece of work in 5 days.When should 5 men leave the work so... (answered by TimothyLamb)
30 men can do a certain work in 15 days. They started working on the project but 5 of... (answered by josgarithmetic,MathTherapy)
20 men can do a piece of work in 24 days. After working for 6 days, additional number of... (answered by richwmiller)
25 men can do a project in 20 days . 15 men leave the project after working for some... (answered by josmiceli)
Q1 ) 24 men working at 8 hours per day can do a piece of work in 15 days. In how many... (answered by Alan3354)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
If 15 men can do a piece of work in 90 days, in how many days can 30 men do the same... (answered by stanbon,richwmiller)
if 20 men can do a piece of work in 8 days, then how many men can finish the same work in (answered by ankor@dixie-net.com)