SOLUTION: For a critical defect, the sampling plan is n = 1,200 and accept/reject = 0/1. If the process is running 0.1% defective, what is the probability of acceptance?In this Question to
Algebra.Com
Question 927201: For a critical defect, the sampling plan is n = 1,200 and accept/reject = 0/1. If the process is running 0.1% defective, what is the probability of acceptance?In this Question to I need to use the Binomial Distribution?
Answer by ewatrrr(24785) (Show Source): You can put this solution on YOUR website!
p(def) = .001, n = 1200
P(x = 0) = binompdf(1200, .001, 0)
0r
P(x = 0) = .999^1200
RELATED QUESTIONS
For a critical defect, the sampling plan is n = 1,200 and accept/reject = 0/1. If the... (answered by ewatrrr)
The Ziteck Corporation buys parts from international suppliers. One part is currently... (answered by textot)
Consider the situation of Review Exercise 5.95.
It has been determined that the sampling (answered by ikleyn)
1. The Ziteck Corporation buys parts from international suppliers. One part is currently... (answered by ikleyn)
A flash drive manufacturer has set a defect standard for their production process. When... (answered by rwm)
Seventeen percent of the components manufactured by a certain process are defective. A... (answered by robertb)
Seventeen percent of the components manufactured by a certain process are defective. A... (answered by Boreal)
You wish to test the following claim (Ha) at a significance level of α=0.05. For the... (answered by Boreal)
Trowbridge Manufacturing produces cases for personal computers and other electronic... (answered by aliza)