SOLUTION: Given the activity mean = 5 and Standard Deviation =1 , Find the probability that the project will take more than 10 weeks to complete

Algebra.Com
Question 751547: Given the activity mean = 5 and Standard Deviation =1 , Find the probability that the project will take more than 10 weeks to complete
Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
Given the activity mean = 5 and Standard Deviation =1 , Find the probability that the project will take more than 10 weeks to complete
----
z(10) = (10-5)/1 = 5
----------
P(x >= 10) = P(z >= 5) = 0.0000002871
================
Cheers,
Stan H.
================

RELATED QUESTIONS

What is the probability that the following project will take more than 13 weeks to... (answered by lynnlo)
What is the probability that the following project will take more than 13 weeks to... (answered by lynnlo)
The time to complete a constructions project is normally distributed with a mean of 60... (answered by solver91311)
The project described in the following table has just begun. It is scheduled to be... (answered by lynnlo)
A random variable is normally distributed. It has a mean of 245 and a standard deviation (answered by CPhill)
Given a test that is normally distributed with a mean of 64 and a standard deviation of (answered by CPhill)
The time taken to complete a statistics final by all students is normally distributed... (answered by ewatrrr)
The project described in the following table has just begun. It is scheduled to be... (answered by lynnlo)
What is the mean of a normal random variable X given that standard deviation is equal to... (answered by stanbon)