Question 1193995: In a bolt factory, machines A, B and C 25%,35% and 40% of total outputs respectively. Of the total of their outputs, 5%,4% and 2% are defective bolts respectively. A bolt is drawn at random and is found to be defective. What is the probability that it was manufactured by machines A, B and C?
Answer by greenestamps(13200)   (Show Source): You can put this solution on YOUR website!


I'll be picky at first....

Each bolt is produced by a single machine. So the probability that a defective bolts was "manufactured by machines A, B, and C" is zero.

ANSWER: 0

-------------------------------------------------------------------------

Now on to answering the question that the problem MEANT to ask....

To avoid working with multiplication of percentages in decimal form, I would choose a convenient number for the total number of bolts produced and work with the resulting whole numbers.

So suppose the total production is 10,000 bolts. Then...

Production:
A: 25% of 10,000 = 2500
B: 35% of 10,000 = 3500
C: 40% of 10,000 = 4000

Faulty bolts:
A: 5% of 2500 = 125
B: 4% of 3500 = 140
C: 2% of 4000 = 80

Total defective bolts: 125+140+80 = 345

P(a defective bolt was produced by machine A) = 125/345
P(a defective bolt was produced by machine B) = 140/345
P(a defective bolt was produced by machine C) = 80/345

Simplify the fractions or convert to decimals as desired/required.


RELATED QUESTIONS

In a razor blade factory, machines A,B and C manufacture 25%, 35% and 40% of the total... (answered by ikleyn)
In a razor balde factory, machines A,B abd C manufacture 25%, 35% and 40% of the total... (answered by ikleyn)
A factory produces its entire output with three machines. Machines I, II, and III produce (answered by jorel1380)
In a certain factory, three machines A, B and C produce the same product. The machines A... (answered by richwmiller)
Three machines A, B and C produce respectively 60%, 30% and 10 % of the total number of... (answered by lynnlo)
Three machines X, Y, Z are produced respectively 50%, 30% and 20% of the total number of... (answered by Theo)
A linear function has a slope of -4/9. Interpret this slope using inputs and outputs (answered by ikleyn)
Kayla works a total of 40 hours each week at two part-time jobs. She works at a... (answered by ewatrrr)
Three different gaming machines are in a line along a wall. The machines guarantee the... (answered by edjones)