Question 1176934: Managers at an automobile manufacturing plant would like to estimate the mean completion time of an assembly line operation, . The managers plan to choose a random sample of completion times and estimate via the sample. Assuming that the standard deviation of the population of completion times is 10.2 minutes, what is the minimum sample size needed for the managers to be 90% confident that their estimate is within 2.0 minutes of ?
Answer by Boreal(15235) (Show Source): You can put this solution on YOUR website!
start with half-interval, which is z*sigma/sqrt(n), and for 90% CI z=1.645
so 1.645*10.2/sqrt(n)=2
and sqrt(n)=1.645*10.2/2
=8.3895
so n=70.38 or 71
RELATED QUESTIONS
Managers at an automobile manufacturing plant would like to estimate the mean completion... (answered by Boreal)
5.)Managers at an automobile manufacturing plant would like to estimate the mean... (answered by ewatrrr)
Can someone please help me solve this? thank you so much
Managers at an automobile... (answered by stanbon)
Managers at an automobile manufacturing plant would like to examine the mean completion... (answered by stanbon)
Managers at an automobile manufacturing plant would like to examine the mean completion... (answered by stanbon)
Please help me to solve this equation. The symbols aren't available on my keyboard that I (answered by Theo)
1.)(a)Consider a t distribution with 29 degrees of freedom. Compute
P<−1.59 (answered by ikleyn)
please help me with this statistical problem. An automobile assembly line operation has a (answered by stanbon)
An automobile assembly line operation has a scheduled mean completion time, , of... (answered by stanbon)