Question 1173866: The completion time of a construction project depends on whether the carpenters and plumbers
working on the project will go on strike. The probabilities of delay are 5%, and 10%, if
carpenters alone go on strike and plumbers alone go on strike, respectively. Also, there is a 30%
chance that plumbers will strike and 20% if carpenters go on strike.
(i) Find the probability of delay occurs?
(ii) If the delay happens what is the probability that the carpenters went on strike?

Answer by ikleyn(52887)   (Show Source): You can put this solution on YOUR website!
.

(i)    P = 0.05*0.2 + 0.1*0.3 = 0.04.



(ii)   P =  =  =  = 0.25 = 25%.

Solved.




RELATED QUESTIONS

A construction project is at present 30 days away from the scheduled completion date.... (answered by CPhill)
Three people who work full-time are to work together on a project, but their total time... (answered by ankor@dixie-net.com)
There are 3 people who work fulltime and are to work together on a project, but their... (answered by ikleyn,richwmiller)
A,B,and C undertook a construction project. A and B worked together the first 6 days and... (answered by ankor@dixie-net.com)
alice can complete a project in 20 days and b0b can complete the same project in 30... (answered by Edwin McCravy)
The time to complete a project is inversely proportional to the number of people who are... (answered by richwmiller)
The time to complete a project is inversely proportional to the number of people who are... (answered by ankor@dixie-net.com)
Working on two projects: And employee is required tospend more time on project X than on (answered by stanbon)
Trying to get my head around normal distribution, please help. The time spent by... (answered by Fombitz)