SOLUTION: Is it C? I want to check my answer. In the following Earliest Start Time (EST) graph, assume each unit of time is an hour. How many hours will it take until Task F can be sta

Algebra.Com
Question 1161191: Is it C? I want to check my answer.
In the following Earliest Start Time (EST) graph, assume each unit of time is an hour.
How many hours will it take until Task F can be started?

A. 7 Hours
B. 8 Hours
C. 14 Hours
D. 4 Hours

The question is provided in the link here: https://i.imgur.com/5fcZDep.png

Answer by MathLover1(20850)   (Show Source): You can put this solution on YOUR website!

yes, it is C. hours

RELATED QUESTIONS

Is it C? I want to check my answer. In the following Earliest Start Time (EST) graph,... (answered by MathLover1)
Hi, I'm new here and hope this is the right topic for my question(s)... I have some... (answered by ankor@dixie-net.com)
Is it D? I want to check my answer. Which graph below has an EULER PATH? A. B. (answered by MathLover1)
When it is noon eastern standard time (EST) in New York City, it is 9:00 AM. Pacific... (answered by Alan3354)
Is it A? I want to check my answers. Which graph below has an EULER CIRCUIT? C.... (answered by solver91311,jim_thompson5910,math_helper)
Is it B? I want to check my answer. Use graph coloring to find the minimum number of... (answered by ikleyn)
Suppose that you have a goal to drive two miles at an average rate of 60 miles per hour.... (answered by nyc_function)
Is it D? I want to check my answer. Which graph below is a tree graph? A. B.... (answered by jim_thompson5910)
Pick two animals to be in a race and answer the following questions. a. Suppose two... (answered by solver91311)