SOLUTION: A previous survey shows that a machine making plastic components is correctly set up for the day's production on 95% of days. On days when it is set up correctly, 98% of the compon

Algebra.Com
Question 1102486: A previous survey shows that a machine making plastic components is correctly set up for the day's production on 95% of days. On days when it is set up correctly, 98% of the components produced are good. If the machine is not set up correctly, only 40% of the components produced are good. On a particular day, the machine is set up and the first component produced is found to be good. What is the probability that the machine is set up correctly?
Answer by Boreal(15235)   (Show Source): You can put this solution on YOUR website!
P(MG|PGood)=P(PGood|MG)*P(MG)/P(Part good|MG)*P(MG)+P(Part good)|MN)*P(MN)
This is 0.98*0.95/(0.98*0.95)+(0.4)*(0.05)=0.931/0.953=0.977 or 97.7%

RELATED QUESTIONS

A previous survey shows that a machine making plastic components is correctly set up for (answered by CPhill,ikleyn)
Question 1 A previous survey shows that a machine making plastic components is correctly (answered by ikleyn)
A machine used in a production process is set up correctly 97% of the time. Given that... (answered by Theo)
6. Each day a quality engineer selects a random sample of 100 bolts from the day’s... (answered by solver91311)
Suppose three machines A, B, and C produce similar engine components. Machine A produces... (answered by Boreal)
In a factory producing disk drives for computers, there are three machines that work... (answered by rothauserc)
It takes 12 minutes to set up a candy making machine. Once the machine is set up, it... (answered by macston)
It takes 24 minutes to set up a candy making machine. Once the machine is set up it... (answered by josmiceli)
It takes 20 minutes to set up a candy making machine. Once the machine is set up, it... (answered by Theo)