Question 769627: Please help me and provide explanation to further understand.
A construction project must be completed in 15 days. Twenty-five workers did one-half of the job in 10 days. How many workers are needed to complete the job on schedule?

Found 2 solutions by ramkikk66, stanbon:
Answer by ramkikk66(644)   (Show Source): You can put this solution on YOUR website!
25 workers completed half the work in 10 days.
Therefore total work = 25 people for 20 days = 500 "person-days" of work.
(To explain, a "person-day" is the unit of work 1 person can complete in 1 day.
So if you have more people, you can complete more person-days of work. If you
have less people, you need to work longer (more "days") to complete the same
person-days" of work.)
Another 250 person-days of work needs to be completed.
But since it needs to be completed in 15 days totally, and 10 days are already
over, this remaining work needs to be completed in 5 days.
i.e. 250 person-days of work needs to be completed in 5 days.
So how many persons do you need? 250 person-days/5 days = 50 people.
Need to add 25 more workers.
Hope you got it :)

Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
A construction project must be completed in 15 days. Twenty-five workers did one-half of the job in 10 days. How many workers are needed to complete the job on schedule?
---------------
# of workers and # of days are inversely related.
----
Note:: "The job" is really (1/2) of the job.
----
n = k/d
--------
25 = k/10
---
k = 250
-----
Equation:
n = 250/d
n = 250/5
n = 50 (# of workers to complete 1/2 the job in 5 days)
================
Cheers,
Stan H.
================

RELATED QUESTIONS

A,B,and C undertook a construction project. A and B worked together the first 6 days and... (answered by ankor@dixie-net.com)
A painting project will take a total of 360 person days to complete. How many days will... (answered by josmiceli)
Please help me and provide explanation to understand further, Uniform Motion... (answered by ramkikk66)
12 Workers can finish a third of a house in 15 days. How many workers must be added to... (answered by Boreal,josmiceli,MathTherapy,ikleyn)
The time to complete a project is inversely proportional to the number of people who are... (answered by josgarithmetic,MathTherapy,stanbon)
10 men completed a construction work in 11 days,15 men completes the same type of... (answered by josmiceli)
If a word problem is asking "You have 9 days to complete a project, in 2 days you... (answered by Alan3354)
I need some help with this word problem. Thanks. One-half of a road construction project (answered by solver91311,stanbon)
Twenty laborers could finish a certain construction job in 35 days. After 11 days, five... (answered by Abbey)