Question 534142: #16
LISA CAN SHOVEL SNOW FROM HER DRIVEWAY IN 65 MINUTES. bILL CAN DO THE DRIVEWAY IN 45 MINUTES. hOW LONG WOULD IT TAKE LISA AND BILL TO SHOVEL THE DRIVEWAY TOGETHER?

Answer by oberobic(2304)   (Show Source): You can put this solution on YOUR website!
Work problems like this are fraction problems.
Lisa does the whole job in 65 minutes, so she does 1/65 of the job per minute.
Bill does 1/45 of the job per minute.
.
(1/65+1/45)*x minutes = 1 whole job completed
.
(45+65)/(45*65) * x = 1
.
110/2925 * x = 1
.
22/585 * x = 1
.
22x = 585
.
x = 585/22
.
x = 26.590 min
.
Working together they can do the job in about 26.6 minutes.
.
Always check your work.
1/45 * 26.6 = .591 = amount of the job done by Bill
1/65 * 26.6 = .409 = amount of the job done by Lisa
Total = 1 whole job.
.
Done.

RELATED QUESTIONS

lisa can shovel snow from her driveway in 60 minutes. bill can do the same in 55 minutes. (answered by Alan3354,DominoEfx,richwmiller)
Lisa can shovel snow from her driveway in 65 minutes. Jim can do the same job in 55... (answered by checkley77)
Janet can shovel snow from her driveway in 45 minutes. Bill can do the same job in 35... (answered by stanbon)
sue can shovel snow from her driveway in 65 minutes. bill can do the same job in 30... (answered by nerdybill)
Mary can shovel snow from her driveway in 40 minutes. Bill can do the same job in 65... (answered by josmiceli,Alan3354)
Lisa can shovel snow from her driveway in 65 minutes. Jim can to the same job in 55... (answered by Alan3354)
Maria can shovel snow from her driveway in 65 minutes. Tom can do the same job in 45... (answered by scott8148,oberobic)
Lisa can shovel snow from her driveway in 35 minutes. Tom can do the same job in 55... (answered by nerdybill)