SOLUTION: Working separately, 5 students make 10 models in 2 days. How many models can 10 students make in 4 days? Email: crewsin1@comcast.net

Algebra.Com
Question 531430: Working separately, 5 students make 10 models in 2 days. How many models can 10 students make in 4 days?
Email: crewsin1@comcast.net

Answer by htmentor(1343)   (Show Source): You can put this solution on YOUR website!
Working separately, 5 students make 10 models in 2 days. How many models can 10 students make in 4 days?
=========================================
The rate is 10 models/(2 days * 5 students) = 1 model per student-day
Therefore, in 4 days 10 students can make
1 model/student-day * 4 days * 10 students = 40 models

RELATED QUESTIONS

working separately, 4 students can do 80 math problems in one hour. at this rate, how... (answered by richwmiller)
If 10 men can make 200 tables working for 15 days at the rate of 8 hr per day, how many... (answered by Edwin McCravy)
5 men can complete a job in 4 days. How many days can 10 men working at 1/4 of the... (answered by josgarithmetic)
There are 4 men making a house. One guy can make it in 2 days , another guy in 10 days,... (answered by josgarithmetic,moemoe)
If 6 people make 4 boxes in 10 days, how many days are needed for 10 people to make 6... (answered by lwsshak3)
Mary can finish an embroidery work in 10 days. After working for 3 days, Mary's cousin... (answered by scott8148)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
I have exam tomorrow. Please help me tutors. 1)AOB is a straight line. Find z if x=35... (answered by fcabanski)
three man can finish a painting job in 8 days. This job can be finished by 5 women in 6... (answered by ankor@dixie-net.com)