SOLUTION: A job can be done by 25 men in 32 days. After 10 days 3 men left. How long will it take the remaining men to finish the job?

Algebra.Com
Question 976597: A job can be done by 25 men in 32 days. After 10 days 3 men left. How long will it take the remaining men to finish the job?
Answer by josgarithmetic(39620)   (Show Source): You can put this solution on YOUR website!
Let r be rate for one man, and let t be the unknown time in the second part of the description, the time quantity asked for.

The second part uses a combination of 25 men and 22 men.


This is the system for the whole description in the form of equations. Use the first equation to get a value for r, and use this to solve for t in the second equation.


;











RELATED QUESTIONS

A job can be done by 25 men in 32 days. After 8 days, 5 men left. how long will it take... (answered by AnlytcPhil,richwmiller,MathTherapy)
A Certain Job Can Be Done By 8 Men In 20 Days. After 5 Days, 3 Men Left The Job. How... (answered by Theo,Fombitz)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)
a piece of work can be done by 40 men in 48 days. after 15 days, 18 men were transferred... (answered by stanbon)
a piece of work can be done by 40 men in 48 days, after 15days, 18 men were transferred... (answered by ankor@dixie-net.com)
Twelve men can finish a job in 16 days. Five men were working at the start, after 8 days... (answered by ankor@dixie-net.com,josgarithmetic)
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
A piece of work can be done by 40 days by 25 men. After 16 days, 13 men are transferred.... (answered by Finavon)
twelve men can finish the job in 20 days. Five men were working at the start and after 10 (answered by lwsshak3)