SOLUTION: ASHA COMPLETES A WORK IN 10 DAYS AND BEENA DOES THE SAME WORK IN 15 DAYS. IN HOW MANY DAYS WILL THEY TOGETHER COMPLETE THE WORK
Algebra.Com
Question 834974: ASHA COMPLETES A WORK IN 10 DAYS AND BEENA DOES THE SAME WORK IN 15 DAYS. IN HOW MANY DAYS WILL THEY TOGETHER COMPLETE THE WORK
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
Add their rates of working
Multiply both sides by
Working together, they complete the
job in 6 days