SOLUTION: 8 workers can complete 2 projects in 9 days. How many workers are needed to complete 5 projects in 12 days?

Algebra.Com
Question 420060: 8 workers can complete 2 projects in 9 days. How many workers are needed to complete 5 projects in 12 days?
Answer by sudhanshu_kmr(1152)   (Show Source): You can put this solution on YOUR website!

for one project 9*8/2 = 36 man days is needed
so, for 5 projects, 36*5 = 180 man days
180/12 = 15
so, 15 workers are needed.

RELATED QUESTIONS

If a job can be completed by 2 workers in 10 days, then what is the number of workers... (answered by stanbon)
12 workers can do a piece of work in 16 days if 12 more workers are added in how many... (answered by Cromlix)
how long will it take 8 workers to complete a job that took 5 workers to complete in 10... (answered by richwmiller)
If 9 workers complete the work in 10 days how many workers will complete the same work in (answered by josgarithmetic,josmiceli)
Hi 5 workers complete a job in 6 days. After 2 days, 3 workers left. how many more days (answered by Theo)
How many workers will be needed to complete a task in 3 days, given that it takes 10 days (answered by edjones)
If 9 workers can complete 12 chairs in 3 days,how long will it take 4 workers to complete (answered by math_helper,ankor@dixie-net.com)
If 9 workers can complete 12 chairs in 3 days, how long will it take 4 workers to... (answered by josgarithmetic,MathTherapy)
Suppose that 5 workers can complete a certain task in 12 days. If there are 15 workers,... (answered by ankor@dixie-net.com)