SOLUTION: Anna can do a piece of work in 12 days. Beth can do the same work in 15 days. Charles can also do the same piece of work in 30 days. Anna starts the work and Beth joins her after 3

Algebra.Com
Question 1157110: Anna can do a piece of work in 12 days. Beth can do the same work in 15 days. Charles can also do the same piece of work in 30 days. Anna starts the work and Beth joins her after 3 days. 3 days before the work is completed Anna leaves and Charles joins the work. In how many days will the work be completed?
Found 2 solutions by josmiceli, MathTherapy:
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
You are given their rates of working:
Anna: [ 1 job ] / [ 12 days ]
Beth: [ 1 job ] / [ 15 days ]
Charles [ 1 job ] / [ 30 days ]
------------------------------------
Anna starts working alone and
works for 3 days. In 3 days she
does this fraction of the job:

There is of the job left
-------------------------------------
Anna and Beth then work together for
an unknown number of days.
Let = the number of days they work together
Their rate of working together is:



The fraction of the remaining work they get done is:

So now is done
is
the fraction left to do
---------------------------
Now for 3 days, Charles and Beth work together
and they finish the job
Add their rates of working





Multiply both sides by



So Anna and Beth worked together for days
------------------------------
Add up the days they all worked:
Anna alone: 3 days
Anna & Beth: 4 days
Charles and Beth: 3 days

They finish the work in 10 days
------------------------------------
Check my math and get a 2nd opinion if needed





Answer by MathTherapy(10551)   (Show Source): You can put this solution on YOUR website!

Anna can do a piece of work in 12 days. Beth can do the same work in 15 days. Charles can also do the same piece of work in 30 days. Anna starts the work and Beth joins her after 3 days. 3 days before the work is completed Anna leaves and Charles joins the work. In how many days will the work be completed?
Anna can do the work in 12 days, or  of work in 1 day
Beth can do the work in 15 days, or  of work in 1 day
Charles can do the work in 30 days, or  of work in 1 day

We already know that Anna worked 3 days, alone, and that Beth and Charles worked 3 days, together.
Therefore, we just need to know how many days Anna and Beth worked together.

Let number of days Anna and Beth worked together, be T
We then get: 

15 + 5T + 4T + 12 + 6 = 60 -------- Multiplying by LCD, 60
5T + 4T + 15 + 12 + 6 = 60
9T + 33 = 60
9T = 27
Time Anna and Beth worked together, or 

Days needed to complete job: 
That’s ALL!!

You can do the check, and if you do, you'll see that the entire job takes 9 days, not 10 as the other person states. 
Plus, his method is very time-consuming and complex - doesn't have to be - and most likely contain errors.

RELATED QUESTIONS

If 15 men can do a piece of work in 90 days, in how many days can 30 men do the same... (answered by stanbon,richwmiller)
Robert can do a piece of work in "x" days. Mary can do the same work in (x+16) days. when (answered by ankor@dixie-net.com,scott8148)
John can do a piece of work in 15 days. John and David can do the same amount work in 6... (answered by Edwin McCravy)
If Mario can do a piece of work in 3 days and Joey in 2 days, in how many days can they... (answered by Alan3354)
10men can paint a room in 6 days how many days can 5men do the same piece of work (answered by stanbon)
2 men can do the same amount of work that 3 boys can do. 4 men and 10 boys can do a piece (answered by josgarithmetic)
Ashraf and Bahar together can do a piece of work in 12 days, which Bahar and Charles... (answered by lwsshak3)
18 boys can do a piece of work in 24 days. In how many days can the 27 boys do the same... (answered by stanbon,sachi)
2 men and 3 women can do a piece of work in 16 days .In how days can 4 men and 6 women do (answered by richwmiller)