SOLUTION: please answer sir,ma'am"mark contracted 15 skilled workers to finish cementing a certain walk of uniform width in 16 days.after 8 days of work,6 of them got sick and were not repla
Algebra.Com
Question 347863: please answer sir,ma'am"mark contracted 15 skilled workers to finish cementing a certain walk of uniform width in 16 days.after 8 days of work,6 of them got sick and were not replaced until 4 days after.he wants the job to be on time .how many should he hire?"
thank you
Found 2 solutions by Fombitz, stanbon:
Answer by Fombitz(32388) (Show Source): You can put this solution on YOUR website!
Originally, the job required worker-days to complete.
They put in worker-days in 8 days.
The reduced crew of put in worker-days in 4 days.
Look at the worker-days remaining.
.
.
.
76 worker-days of output are required to finish the job.
He has used up days aleready and he has 4 days if he wants to stick to the 16 day schedule.
He needs to have workers to make his schedule.
Since he's already hired workers, he should hire an additional workers.
Answer by stanbon(75887) (Show Source): You can put this solution on YOUR website!
mark contracted 15 skilled workers to finish cementing a certain walk of uniform width in 16 days.
---
Total man-days is 15*16 = 240
-----------------
after 8 days of work 15*8 = 120 man-days of work are completed
----
With 6 men sick for 3 days, the 9 men complete 9*3 = 27 man-days
of work, leaving 93 man-days still to be done.
he wants the job to be on time .how many should he hire?"
---------------
There are 4 days remaining to do 223 man-days of work
93/4 = 24 1/4 men
---
He needs 10 additional men.
=============================
Cheers,
Stan H.
RELATED QUESTIONS
A certain factory employs 600 skilled and 450 unskilled workers. If a skilled worker is... (answered by stanbon)
A commercial building was built in 1 - 7/8 months by 20 skilled workers and 30 unskilled... (answered by ankor@dixie-net.com)
Hi
it takes 15 days for 10 workers working 8 hours a day to finish an order. How many... (answered by joshuajz,josgarithmetic,ikleyn,greenestamps)
On the first day of the year, Mr. John deposits 1,000 dollars in a bank at interest rate... (answered by Theo)
Working together, 4 skilled workers can complete a job in 5 days. However, 5 semi-skilled (answered by ankor@dixie-net.com)
4 skilled workers can do a job in 5 days, 5 semi-skilled workers can do the same job in 6 (answered by josgarithmetic)
In a factory , 10 workers were engaged to finish a piece of work in a certain number of... (answered by richwmiller)
4 skilled workers can do a job in 5 days. 5 semi skilled worers can do
The same job in... (answered by josgarithmetic)
4 skilled workers can complete a job in 5 days. 5 semi-skilled workers can complete the... (answered by josgarithmetic,ikleyn)