SOLUTION: One crew can put up holiday decorations in the mall in 9 hours. A second crew can put up the decorations in 7 hours. How long will it take if both crews work together to decorate t

Algebra.Com
Question 16110: One crew can put up holiday decorations in the mall in 9 hours. A second crew can put up the decorations in 7 hours. How long will it take if both crews work together to decorate the mall? Please enter your answer as a number without the units.
Answer by fractalier(6550)   (Show Source): You can put this solution on YOUR website!
We use the equation
t/A + t/B = 1
now plug in to solve for t...
t/7 + t/9 = 1
multiply by the LCD, 63, and get
9t + 7t = 63
16t = 63
t = 63/16 hours or
t = 3 15/16 hours if you need it mixed...

RELATED QUESTIONS

One crew can put up holiday decorations in the mall in 8 hours. If a slower crew can put... (answered by Alan3354,ikleyn)
A painting crew can paint 4 room in 7 hours. If the crew works at the rate, how many... (answered by josmiceli)
A library crew can shelve books in eight hours. another crew can do the job in six hours. (answered by lwsshak3)
A library crew can shelve books in six hours. Another crew can do the job in four hours.... (answered by josmiceli)
A roofing crew can roof a house in 10 hours. If a second crew was added, the job would... (answered by CharlesG2)
A library crew can shelf books in six hours. Another crew can do the job in four hours.... (answered by lwsshak3)
A 3-men crew can do a certain job in 4 hours, while it takes a 4-men crew to do the same... (answered by ankor@dixie-net.com)
A crew of 2 could put siding on a house in 30 hours. Another crew of 3 could do the same... (answered by josmiceli,greenestamps)
One roofing crew can finish a 2,800-square-foot roof in 12 hours, and another crew can do (answered by josgarithmetic)