SOLUTION: 50 labour can dig a pond in 16 days . How many laboures will be required to dig another pond, double in size in 20 days.

Algebra.Com
Question 950680: 50 labour can dig a pond in 16 days . How many laboures will be required to dig another pond, double in size in 20 days.
Found 2 solutions by ankor@dixie-net.com, macston:
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
50 labour can dig a pond in 16 days .
Find how many man-days to dig the pond
50 * 16 = 800 man-days
:
How many laboures will be required to dig another pond, double in size in 20 days.
Assume a pond double in size requires 1600 man-days
let m - number of men required to do this 20 days
20m = 1600
m = 1600/20
m = 80 men required

Answer by macston(5194)   (Show Source): You can put this solution on YOUR website!
1 pond/16 days=1/16 pond/day Fifty laborers dig 1/16th pond per day.
(1/16 pond/day)/50 laborers=1/800 pond per day per laborer Each laborer digs 1/800 pond per day.
To dig a pond double that, basically 2 ponds in 20 days is 2 ponds/20 days=1/10 pond/day.
(1/10 pond/day)/(1/800 pond/day/laborer)=80 laborers
ANSWER It would require 80 laborers to dig a pond twice the size in 20 days

RELATED QUESTIONS

if a 12 men can dig in a pond in 8 days how many can dig it in 6 days? (answered by lwsshak3,saw,greenestamps,ikleyn,Alan3354)
6 men can dig a trench in 3 days. How many days will it take 9 men to dig the same trench (answered by Edwin McCravy)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
If 12 men can dig a trench in 8 days how many men can dig it in 6... (answered by josgarithmetic,greenestamps)
25 men dig a canal in 21 days. In how many days will 15 men dig it? (answered by macston)
7 men can dig a drain in 10 days. how many men would dig the same drain in 14 days (answered by josgarithmetic,ikleyn,greenestamps)
In the middle of a round pond floats a lovely pond-plant. The size of the pond-plant... (answered by Alan3354)
Ten workers can dig 20 holes in 40 days. At the same rate, how many days would twenty... (answered by josgarithmetic)
20 men can dig a tank 40 feet long and 30 feet broad and 10 feet deep in 25 days. In how... (answered by Solver92311,ikleyn)