SOLUTION: A can do a job in 6 days while B can do a job in 8 days. They worked together for 2 days when B left the job. How much time will A require to complete the work?
Algebra.Com
Question 841797: A can do a job in 6 days while B can do a job in 8 days. They worked together for 2 days when B left the job. How much time will A require to complete the work?
Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
2/6+2/8+x/6=1
1/3+1/4+x/6=1
x/6+7/12 = 1
x/6=5/12
2x/12=5/12
2x=5
x=2.5 more hours to finish
RELATED QUESTIONS
mr a can do a job for 3 days while mr b can do the same job for 6 days. if the two of... (answered by stanbon)
. If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ankor@dixie-net.com)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by jorel1380)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ntnk)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
A does a job in 6 days while B can do the same job in 4 days. how long will it take A and (answered by josgarithmetic)
sam can do job in 4 days, Lisa - 6 days, Tom - 2 days. How long would the job take to... (answered by ewatrrr)
ryan can do a job in 12 days. after he has worked for 4 days ,he is joined by sandy.they... (answered by richwmiller)