Question 1199446: If 20 men can lay 36 m of pipe in 8 hours. How long would 25 men take to lay the next 54 m of pipe
Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
N, how many workers
R, work rate for 1 worker
T, time of working
W, amount of work
----basic rule


let r be the work rate of any one man, and x be the time asked for.



If you divide the second equation by the first equation,..........






RELATED QUESTIONS

If it takes 3 man 4 days to lay 400 feet of pipe, how many men will it take to lay 2400... (answered by josmiceli)
A can lay a lawn in 10 hours, B can lay a lawn in 8 hours. What fraction of the lawn... (answered by ewatrrr)
A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they... (answered by ankor@dixie-net.com)
A contractor agrees to lay a road 3000 m long in 30 days. 50 men are employed and they... (answered by ankor@dixie-net.com)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,ikleyn)
It takes 8 men 9 days to lay out a garden how long will it take 6 men to lay out similar... (answered by josmiceli,richwmiller)
A contractor agrees to lay a road 3000m long in 30 days. 50 men are employed and they... (answered by josgarithmetic,MathTherapy)
A large pipe can be filled by one pipe in 20 hours. A second pipe can be fill the tanks... (answered by josgarithmetic)
Jerry can lay a tile floor in 3 hours less time than Jake. If they can work together, the (answered by Theo,MathTherapy)