SOLUTION: one machine can complease a job in 10 minutes if the same job is done by this machine and an older machine working together the two job can be completed in 6 minutes. how long
Algebra.Com
Question 1171222: one machine can complease a job in 10 minutes if the same job is done by this machine and an older machine working together the two job can be completed in 6 minutes. how long
Found 3 solutions by MathLover1, josgarithmetic, greenestamps:
Answer by MathLover1(20850) (Show Source): You can put this solution on YOUR website!
Machine : minutes
rate of job in minute
Machine minutes
they do of the job in minute
Job done by in minute =
=
=
=
so machine will take minutes to do the same job
Answer by josgarithmetic(39620) (Show Source): You can put this solution on YOUR website!
-----------------------------------------------------------------------
one machine can complease a job in 10 minutes if the same job is done by this machine and an older machine working together the two job can be completed in 6 minutes.
----------------------------------------------------------------------
Maybe this is written better:
--------------------------------------------------------------------
One machine can complete a job in 10 minutes. If the same job is done by this machine and an older machine working together the job can be completed in 6 minutes.
-----------------------------------------------------------------
If this is really the way you mean the problem then:
-------------minutes if just the older machine does 1 job alone.
Answer by greenestamps(13203) (Show Source): You can put this solution on YOUR website!
If a formal algebraic solution is not required....
The newer machine can do the job alone in 10 minutes.
So when the two machines together do the job in 6 minutes, the newer machine does 6/10 = 3/5 of the job.
That means in those 6 minutes the older machine does 2/5 of the job.
2/5 of the job in 6 minutes means the older machine can do the whole job alone in (5/2)*6 = 15 minutes.
RELATED QUESTIONS
one machine can complete a job in 10minutes. if the same jobis done byh thismachine and... (answered by mananth)
Machine A can do a job alone in 10 hours. Machine B can do the same job alone in 12... (answered by Boreal,ikleyn,math_tutor2020)
a new machine that deposits cement for a road requires 12 hours to complete one-half mile (answered by josgarithmetic)
At a soda bottling plant one bottling plant machine can fulfill the daily quota in 10... (answered by josgarithmetic)
A new automatic machine can do a job in 1 hour less than an older machine. Together they... (answered by TimothyLamb)
A new copying machine can do a certain job in 1 hour less than an older copier. Together... (answered by ankor@dixie-net.com)
A new machine takes one-third the time to complete a certain job that an old machine... (answered by Paul)
an older machine can do a job in 104 minuets, it takes only 40 minuets when a newer... (answered by nerdybill,oberobic)
A print shop can print the MVP math book in 24 minutes if both of their print machines... (answered by josgarithmetic)