Question 1138183: A contractoremploys 119 men to build a factory.After 44days 2/3 of building is
Completed.He then employs 35 more men.How long will it take to complete the work.

Answer by greenestamps(13200)   (Show Source): You can put this solution on YOUR website!


After 44 days, 1/3 of the factory is still to be built. The 119 men could finish the factory in another 22 days.

The number of man-days required to finish building the factory is then 119*22. If 35 more men are hired, then the number of men on the job will be 119+35 = 154; the number of days it will take to finish the job is then



ANSWER: It will take 17 more days to finish building the factory.

RELATED QUESTIONS

A contractor undertook to build a building in 52 days and employed 24 men to work. Only... (answered by ankor@dixie-net.com,josgarithmetic)
A contractor undertakes to build a bridge 12 km long in 350 days and employs 45 men. At... (answered by josgarithmetic,MathTherapy)
a contractor decides that he can build a barn in 8 weeks using 5 men. if he employs 3... (answered by Fombitz,ewatrrr)
4 men and 10 women were put on a work. They completed 1/3 of the work in 4 days. After... (answered by josgarithmetic)
A man decides to build a road of 150 km in 300 days an employee 45 men. After 100... (answered by richwmiller)
a contractor got a contract to build a building in 30 days and employed 20 men to do the... (answered by ankor@dixie-net.com)
A contructor undertakes to build a wall 1000 meter long in 50 days. He employed 56 men... (answered by stanbon,ankor@dixie-net.com,MathTherapy)
A contractor undertakes to dig a canal, 6 kilometer long in 35 days and employed 90 men.... (answered by macston)
The ratio of men to women in a certain factory is 3 to 4. There are 204... (answered by Alan3354)