Question 1094224: 2 men and 7 boys complete a work in 14 days .3 men and 8 boys complete it in 11 days.then in how many days will 8 men and 6 boys complete the work ?

Answer by ikleyn(52787)   (Show Source): You can put this solution on YOUR website!
.
Let M be the rate of work for a man and B be the rate of work for a boy.
Then from the condition you have this system of equations

2M + 7B = ,     (eq1)
3M + 8B = .     (eq2)


Solve the system (it is just a technique) and find M and B.


Then evaluate 8M + 6B and calculate reciprocal.

For similar problems, see the lesson
    - Solving rate of work problem by reducing to a system of linear equations
in this site.


RELATED QUESTIONS

If 6 men and 8 boys can complete a piece of work in 10 days and 8 men and 6 boys can... (answered by ikleyn)
4 men & 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in (answered by josgarithmetic)
3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to... (answered by josmiceli)
4 men and 6 women can complete a work in 8 days while 3 and 7 women can complete it in 10 (answered by ankor@dixie-net.com)
If 4 men or 7 boys can do a work in 29 days, then 12 men and 8 boys will do the same work (answered by ankor@dixie-net.com)
2 men can do the same amount of work that 3 boys can do. 4 men and 10 boys can do a piece (answered by josgarithmetic)
If 8 men and 17 boys can do a piece of work in 26 days how many days will it take 4 men... (answered by richwmiller,Vladdroid)
if 3 men or 6 boys can do piece of work in 20 days.how many days will 6 men and 8 boys... (answered by ankor@dixie-net.com)
If 2 men and 3 women can complete a task in 8 days; and 4 men and 5 women can complete a... (answered by Edwin McCravy)