I believe that 7 more workers are needed:
5 men are hired to complete a job. If one more man is hired, the
job can be completed 8 days earlier. Assuming that all the men
work at the same rate, how many more men should be hired so that
the job can be completed 28 days earlier?
Use the worker-time-job formula, which is:
where
W1 = the number of workers in the first situation.
T1 = the number of time units (days in this case) in the first situation.
J1 = the number of jobs in the first situation.
W2 = the number of workers in the second situation.
T2 = the number of time units (days in this case) in the second situation.
J2 = the number of jobs in the second situation.
W1 = 5 W2 = 6
T1 = x days T2 = x-8 days
J1 = 1 J2 = 1
So it takes 48 days for 5 workers to do the job.
Now we use the worker-time-job formula again with N more workers than 5,
or 5+N workers, and 28 days less than 48 or 10 days.
this time with
W1 = 5 W2 = 5+N
T1 = 48 days T2 = 48-28=20 days
J1 = 1 J2 = 1
So 7 more workers will be needed.
Edwin
.
5 men are hired to complete a job. If one more man is hired, the job can be completed 8 days earlier.
Assuming that all the men work at the same rate, how many more men should be hired so that the job can be completed 28 days earlier?
~~~~~~~~~~~~~~~~~~~~~~~
Let "a" be the rate of work of one worker per day.
Then the number of days for 5 workers to complete the job is ;
the number of days for 6 workers to complete the job is .
Thus, we can write this time equation
- = 8 days. (1)
It implies
- = 8,
= 8,
a = . (2)
+--------------------------------------------------------------+
| So, we found that under given condition the rate of work |
| is 1/240 of the job per day for each worker. |
+--------------------------------------------------------------+
Now we want to find the number n of additional workers (to 5 workers) to complete
the job 32 days earlier. For it, we write similar time equation to (1)
- = 28.
Substitute here a = 1/240, based on (2). You will get
- = 28.
To solve, simplify step by step. You will get
48 - = 28,
48 - 28 = ,
20 =
5 + n =
5 + n = 12.
n = 12 - 5 = 7.
+----------------------------------------------------------------+
| Second part of the solution can be worded in different way. |
+----------------------------------------------------------------+
We just found that the rate of work of one worker is 1/240 of the job per day.
It means that the entire job is 240 man-days.
5 workers can complete this job in 240/5 = 48 days.
We want the job be complete in 48-28 = 20 days.
Hence, 240/20 = 12 workers are needed, i.e. 12 - 5 = 7 workers should be added.
ANSWER. 7 workers should be hired in addition to the original 5 workers to complete the job 28 days earlier.
Solved.