Question 757463: If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
the Answer was given as 4. can you show me how this answer was reached?

Answer by John10(297)   (Show Source): You can put this solution on YOUR website!
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
-------------------------------
As you know that the larger group of people will complete faster than smaller group of people. Thus it is relatively inverse
Let D is number of days and N is number of men
N = k/D
6 = k/14
==>k = 6 * 14 = 84
If we have D = 21 days then
N = k/D = 84/21 = 4 men.
Hope it helps! John

RELATED QUESTIONS

If 6 men can do a piece of work in 14 days, how many men are needed to do the same work... (answered by tutorcecilia,ptaylor)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in... (answered by stanbon)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by josmiceli)
if 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by JimboP1977)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by flame8855,Alan3354)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by solver91311)
If 6 men can do a piece of work in 4 days, how many men are needed to do the work in 21... (answered by ankor@dixie-net.com)
If 6 men can do a piece of work in 14 days, how many men are needed to do work in 21... (answered by scott8148,RAY100)
This problem was on a pre-employment exam. If 6 men can do a piece of work in 14 days, (answered by Earlsdon,ankor@dixie-net.com)