Question 370682: A and Bcan do a piece of work in 12 days, B and C in 10 days and A and C in 15 days. How long will each take to do work seprately

Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
A and B can do a piece of work in 12 days, B and C in 10 days and A and C in 15 days. How long will each take to do work separately
-------------
Rate Equations:
1/A + 1/B + 0 = 1/12
0 + 1/B + 1/C = 1/10
1/A + 0 + 1/C = 1/15
----
Using a matrix method I get:
1/A = 1/40
1/B = 7/120
1/C = 1/24
===========
Days to do the job alone:
A = 40 days
B = 120/7 = 17.14 days
C = 24 days
=====================
Cheers,
Stan H.


RELATED QUESTIONS

A, B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in... (answered by josmiceli)
A,B and C do a piece of work in 10 days. A and B can do it in 12 days. A and C in 20... (answered by savvyhush23)
A,B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in 20 (answered by dkppathak)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)
a and b can each do a piece of work in 15 days and 18 days. if a works for 10 days, how... (answered by stanbon)
.A and B can do a piece of work in 12 days,B and C can do it in 15 days and C and A can... (answered by ankor@dixie-net.com)
A and B can do a piece of work in 12 days, B and C can do it in 15 days and C and A can... (answered by solver91311)
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days. They work... (answered by richwmiller)