Question 361208: A can do a piece of work in 20 days which B can do it in 12 days. B worked at it for 9 days. A can finish remaining work in:
a)3
b)5
c)7
d)11

Answer by mananth(16946)   (Show Source): You can put this solution on YOUR website!
B does the job in 12 days
so he does 1/12 of the job in 1 day.
so he does 9/12 of the job in 9 days = 3/4 of the job.
balance job will be 1/4
...
A does the job in 20 days
so he does 1/20 of the job in 1 day.
1/4 of the job he will take
..
(1/4)/(1/20)
1/4 *20 =5 days
m.ananth@hotmail.ca

RELATED QUESTIONS

A can do a piece of work in 16 days and B can do it in 20 days. These worked together for (answered by robertb)
a and b can do a piece of work in 18 days, b and c can do it in 24 days while c and a... (answered by ikleyn)
A, B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in... (answered by josmiceli)
A,B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in 20 (answered by dkppathak)
A and B together can finish a piece of work in 12 days. it A alone can finish the same... (answered by ankor@dixie-net.com)
A and B can do a piece of work in 12 days , B and C can do it in 15 days and C and A can... (answered by richwmiller)
A and B together can do a piece of work in 12 days, which B and C together can do in 16... (answered by KMST)
A,B and C do a piece of work in 10 days. A and B can do it in 12 days. A and C in 20... (answered by savvyhush23)
If 4 men and 6 boys can finish a piece of work in 24 days, in what time will 8 men and 9... (answered by ankor@dixie-net.com)