put this solution on YOUR website!Sally can paint 1/4 of the job per hour
John can paint 1/6 of the job per hour
:
together the can paint (1/4+1/6)of the job per hour
:
LCM is 24
:
6/24+4/24=10/24=5/12( of the job per hour(together))
:
5/12(t)=1(job)
:
cross multiply
:
5t=12
:

hours to complete job together