SOLUTION: Mr.X can finish a job in nine hours. After working for five hours, he decided to stop. Mr.Y helped Mr. X and finished the job in 2 hours and 20 minutes. How long would it take Mr.
Algebra.Com
Question 915668: Mr.X can finish a job in nine hours. After working for five hours, he decided to stop. Mr.Y helped Mr. X and finished the job in 2 hours and 20 minutes. How long would it take Mr. Y to do the job alone?
Found 2 solutions by josgarithmetic, stanbon:
Answer by josgarithmetic(39614) (Show Source): You can put this solution on YOUR website!
RATES AS JOBS per HOUR
Mr. X,
Mr. Y,
Mr. X&Y,
The one whole job done:
.
The reason the equation is composed that way is because Mr. X (he) decided to stop. When Mr. Y helped, he and Mr. X were not working on the job at the same time.
Solve the equation for y.
HOURS for Mr. Y to do the job alone.
Answer by stanbon(75887) (Show Source): You can put this solution on YOUR website!
Mr.X can finish a job in nine hours. After working for five hours, he decided to stop. Mr.Y helped Mr. X and finished the job in 2 hours and 20 minutes. How long would it take Mr. Y to do the job alone?
-----
X's rate:: 1/9 job/hr
------------------
In 5 hrs X does 5/9 of the job.
=====
Let Y's time to do the job alone be "x"; his rate is 1/x job/hr
----
Note:: 2 hr and 20 min = 2 hr and (1/3)hr = 7/3 hrs.
---------------------------------------------------
Together rate is 1/(7/3) = 3/7 job/hr
-----
Equation to solve for "x":
work + work = 1 job
---
(5/9)+ (1/9 + 1/x)(3/7) = 1 job
------
[(x+9)/x](3/7) = 4/9
(x+9)/x = (4/9)(7/3)
(x+9)/x = 28/27
28x = 27x+9*27
x = 81 hrs (time for "y" to do the job alone)
================
Cheers,
Stan H.
------------------
RELATED QUESTIONS
In solving the problem below, use a variable/s to represent the unknown quantity or... (answered by josgarithmetic)
Mr. Alan can finish a job in 3 hours by himself,And Mr. Brian can finish the job by... (answered by richwmiller)
Mr. Poly Nomial takes 8 hours to paint his room. After working for one hour, he called... (answered by macston,stanbon)
Mr. I does a job in x hours while Mr. L can do it in y hours. How much of the job could... (answered by ikleyn)
Mr. Reyes estimates he can do a job in 12 hours while Mr. Tan estimates he can do the... (answered by edjones)
solve. Round to the nearest tenth of necessary
Mr. Jansen can shingle a roof in... (answered by josmiceli)
Mr. Wallace can paint a fence in 2 hours. His son Greg can paint the fence in 6 hours.... (answered by CharlesG2)
Working together, Mr. Kent and Mr. Wayne can complete a job in 5 hours. If Mr. Wayne... (answered by Theo,richwmiller)
Please help me solve this:
Two prisoners have the task of digging a grave in the... (answered by Edwin McCravy)